Response 3686566

Response to request for information

Reference

3686566

Response date

9 April 2029

Request

  1. How many Section106 (S106) agreements were completed in financial years a) 2022-23, b) 2023-24 and c) 2024-25?
  2. What was the average time taken from a planning application being validated to the completion of an associated S106 agreement in a) 2022-23, b) 2023-24 and c) 2024-25?
  3. What was the longest and shortest duration taken to complete an S106 agreement in a) 2022-23, b) 2023-24 and c) 2024-25?
  4. Do you have any internal targets or key performance indicators (KPIs) for S106 negotiation timescales? If so, please provide details.
  5. How many S106 agreements took longer than 12 months to be agreed a) 2022-23, b) 2023-24 and c) 2024-25?
  6. How many planning applications lapsed or were withdrawn due to delays in S106 negotiations in a) 2022-23, b) 2023-24 and c) 2024-25?
  7. How much was spent on external legal consultants on work to negotiate S106 agreements in a) 2022-23, b) 2023-24 and c) 2024-25?

Response

Section 106 agreements were completed as follows:

  • 2022-2023: 10
  • 2023-2024: 5
  • 2024-2025: 11

For the avoidance of doubt these figures include Deeds of Variation to existing S016 Agreements as well as Unilateral Undertakings made between the specified dates.

In response to your other queries, we do not hold the information requested.